Our achievements

JACIR has carried out the complete renovation of concrete cooling towers even across the oceans.

On Reunion Island, JACIR has only kept the frame of 6 cells of 40m2 each and has ensured a complete refurbishment while improving the performance of the towers.

This project required:
  • 5 months of studies,
  • 172,000 parts designed,
  • 1.850 hours of fabrication and preparation,
  • 12 containers,
  • 4 site supervisors for 8 weeks.